KLK476: Development of Enhancements to the AutoPayItem (API)
Software Tool
ITD Research Project 116A
Principal Investigators:
Michael Kyte
Project Objectives:
Develop, test and implement enhancements to the
API software tool. Jeff Greenberg, consultant, and the NIATT
software development staff, will jointly develop these enhancements.
Task Descriptions:
Task 1: Software requirements: Prepare a
memorandum that summarizes the requirements for this project.
This memorandum will be prepared by the consultant and NIATT and
reviewed and approved by Idaho Transportation Department. Task 1
will be completed before the remainder of the task will be
undertaken
Task 2: Sidebar Summary Capsule/Text:
Rewrite the sidebar summary so that it will work at any scale.
The new code will be modular and well commented.
Task 3: Build prototype: Build a prototype
to determine if the desire dynamic pay item functionality is
possible. Complete the prototype and integrate it into API.
Task 4: Training: Review final design and
code with NIATT software development staff and provide training
on related MDL issues.
Budget Information:
Total project cost, including UI matching
funds, was $11,526
Project status:
Complete |